| Auxiliary blower - clean impeller and casing |
24,000 h |
clean |
Maker |
| Auxiliary blower - replace ball bearing |
24,000 h |
replace |
Maker |
| Axial damper - dismantling and inspection |
36,000 h |
overhaul |
Maker |
| Bedplate - check pre-tension of foundation bolts |
12,000 h |
check |
Maker |
| Bedplate - check pre-tension of foundation bolts (first time) |
1,500 h |
initial |
Maker |
| Common start valve - overhaul |
18,000 h |
overhaul |
Maker |
| Connecting rod - inspect bottom end bearing |
30,000 h |
inspect |
Maker |
| Connecting rod - inspect top end bearing |
30,000 h |
inspect |
Maker |
| Connecting rod bearings - check bearing clearances |
6,000 h |
check |
Maker |
| Control air filter - clean |
6,000 h |
clean |
Maker |
| Control air filter - drain |
1 weeks |
clean |
Maker |
| Cooling water - determine quality, inhibitor concentration and pH |
1 weeks |
analyse |
Maker |
| Crank angle sensor - replace |
36,000 h |
replace |
Maker |
| Crank angle sensor unit - check pre-tension of toothed belt |
3,000 h |
check |
Maker |
| Crank angle sensor unit - check pre-tension of toothed belt (first time) |
1 h |
initial |
Maker |
| Crank angle sensor unit - overhaul drive |
36,000 h |
overhaul |
Maker |
| Crank angle sensor unit - replace toothed belt |
36,000 h |
replace |
Maker |
| Crank angle sensor unit - visual lube oil check |
1,500 h |
check |
Maker |
| Crankcase - visual examination |
1,500 h |
inspect |
Maker |
| Crankshaft - measure crank deflection |
6,000 h |
inspect |
Maker |
| Driving wheels - check condition of teeth |
6,000 h |
check |
Maker |
| Driving wheels - check running clearance and backlash of teeth |
6,000 h |
check |
Maker |
| Engine stays with friction shims - check pre-tension of screws |
6,000 h |
check |
Maker |
| Exhaust valve - check condition and wear of valve seat |
24,000 h |
inspect |
Maker |
| Exhaust valve - check condition and wear of valve spindle |
24,000 h |
inspect |
Maker |
| Exhaust valve - check piston seal ring / rod seal ring / guide bush |
24,000 h |
check |
Maker |
| Exhaust valve control unit - random check of piston and slide rod |
18,000 h |
check |
Maker |
| Exhaust valve control unit - replace filter |
18,000 h |
replace |
Maker |
| Exhaust valve control unit - replace rail valve (pre-control valve) |
30,000 h |
replace |
Maker |
| Exhaust valve drive - random check of pistons, damper and thrust piece |
18,000 h |
check |
Maker |
| Fuel overpressure safety valve - function check on test bench |
18,000 h |
test |
Maker |
| Fuel pressure control valve - check shut-down function |
3,000 h |
test |
Maker |
| Fuel pressure control valve - function check |
6,000 h |
test |
Maker |
| Fuel pressure control valve - general overhaul |
36,000 h |
overhaul |
Maker |
| Fuel pump - random visual check of plunger, cylinder, roller and roller guide |
18,000 h |
check |
Maker |
| Fuel pump - replace O-rings in valve block |
18,000 h |
replace |
Maker |
| Fuel pump actuator arrangement - check connecting elements and lubricate |
3,000 h |
check |
Maker |
| Fuel pump unit camshaft - check bearing clearances at random |
12,000 h |
check |
Maker |
| Fuel pump unit camshaft - check running surface of cams (first time) |
500 h |
initial |
Maker |
| Fuel pump unit camshaft - check running surface of cams, rollers and roller guides |
3,000 h |
check |
Maker |
| Fuel pump unit camshaft - check thrust bearing clearances |
36,000 h |
check |
Maker |
| Guide shoe / crosshead pin - check clearances |
6,000 h |
check |
Maker |
| Injection control unit - replace filter |
18,000 h |
replace |
Maker |
| Injection control unit - replace unit including rail valves |
24,000 h |
replace |
Maker |
| Injection valve - check spray pattern, opening pressure and tightness |
3,000 h |
test |
Maker |
| Lubricating oil - laboratory analysis |
3,000 h |
analyse |
Maker |
| Main bearing - remove bearing upper half for inspection |
12,000 h |
inspect |
Maker |
| Oil mist detector - follow manufacturer's instructions |
6 months |
check |
Maker |
| Piston - dismantle and assemble, open and clean cooling space |
3 years |
overhaul |
Maker |
| Piston - remove, clean and measure ring grooves |
18,000 h |
overhaul |
Maker |
| Piston / rings / liner - visual check through scavenge ports |
1,500 h |
inspect |
Maker |
| Piston rings - replace all piston rings |
18,000 h |
replace |
Maker |
| Piston underside - check condition of space and clean |
1,500 h |
clean |
Maker |
| Piston underside - check drains for free passage |
1,500 h |
check |
Maker |
| Pressure gauges and pyrometers - compare and calibrate against master instruments |
6,000 h |
calibrate |
Maker |
| Scavenge air cooler - check condensate collector through sight glass |
1 days |
check |
Maker |
| Scavenge air cooler - check condensate collector/filter for free passage |
1,500 h |
check |
Maker |
| Scavenge air cooler - check sealing |
3 months |
check |
Maker |
| Scavenge air cooler - vent |
1 days |
clean |
Maker |
| Scavenge air receiver - check and clean air flaps |
4,000 h |
clean |
Maker |
| Scavenge air receiver - check water drain pipings for free passage |
1,500 h |
check |
Maker |
| Scavenge air receiver - clean receiver |
4,000 h |
clean |
Maker |
| Servo oil non-return valve - random check |
18,000 h |
check |
Maker |
| Servo oil rail - replace hoses |
18,000 h |
replace |
Maker |
| Servo pump unit - check bearing bushes to pinion |
24,000 h |
check |
Maker |
| Servo pump unit - check pinion and driving wheels to servo pump drive |
3,000 h |
check |
Maker |
| Servo pump unit - replace servo oil pump |
24,000 h |
replace |
Maker |
| Start interlock - check electric and pneumatic interlocks |
3 months |
test |
Maker |
| Starting air shut-off valve - dismantle, clean and check |
24,000 h |
overhaul |
Maker |
| Starting valve - check piping before the valve during operation |
1 weeks |
check |
Maker |
| Starting valve - remove and dismantle one valve at random |
6,000 h |
overhaul |
Maker |
| Starting valve solenoid valve - overhaul |
18,000 h |
overhaul |
Maker |
| Starting valve solenoid valve - random check |
6,000 h |
check |
Maker |
| Thrust bearing - check axial and radial clearances |
6,000 h |
check |
Maker |
| Thrust bearing - check bottom drain for free passage |
6,000 h |
check |
Maker |
| Tie rod - check pre-tension (first time) |
1 years |
initial |
Maker |
| Tie rod - check pre-tension, re-tension if necessary |
24,000 h |
check |
Maker |
| Torsional vibration damper - take silicon oil sample (first time) |
15,000 h |
initial |
Maker |
| Turbocharger air filter - check |
6 months |
check |
Maker |
| Turning gear - check screwed connections |
12,000 h |
check |
Maker |
| Turning gear - check screwed connections (first time) |
1 years |
initial |
Maker |
| Turning gear - re-lubricate tooth flanks of pinion and flywheel |
2,000 h |
clean |
Maker |
| WECS electronic components - replace FCM-20 module |
36,000 h |
replace |
Maker |
| WECS electronic components - visual cabling check |
3 months |
check |
Maker |
| Water separator - check condensate collector through sight glass |
1 days |
check |
Maker |
| Water separator - check condensate collector/filter for free passage |
1,500 h |
check |
Maker |
| Water separator - check elements |
1,500 h |
check |
Maker |